Manifolds, SSIV’s & Caissons
The Telford field was discovered in a location 9 km to the south of the Amerada Hess Scott Platform. The field was developed using subsea hardware tied back to the already existing production facilities in the Scott field.
The Yard was awarded a contract to manufacture two 200 Tonne Manifolds, a 100 Tonne Subsea Isolation Valve (SSIV) Cage, a 400 tonne Caisson and 70 tie-in spools. Following a tight fabrication programme the structures were loaded out in early Summer 1996.